Question
1 Approved Answer
please walk me through this question the anwser is 300 but i dont know how to get there The three tables above shows the master
please walk me through this question the anwser is 300 but i dont know how to get there The three tables above shows the master production schedule and the bill of materials of part A, and the inventory records of all the parts. There are no scheduled receipts. Given this information, what is the planned order receipt of part C in Week 6?(Only enter a number. Do not enter any units
please walk me through this question the anwser is 300 but i dont know how to get there