Answered step by step
Verified Expert Solution
Question
1 Approved Answer
pm 592 homework 6-1 - earned value calculations. please help me find the answer PM592 Week 6 Homework Assignment 6-1: Earned Value calculations (Graded 25
pm 592 homework 6-1 - earned value calculations. please help me find the answer PM592 Week 6 Homework Assignment 6-1: Earned Value calculations (Graded 25 Points) Problems Based on the following Project data, answer the questions a and b Activity Duration Predecessors Task 7 days 10 days 8 days B 10 days A 7 days B 4 days D Budget $16,850 $22,500 $16,000 $12,790 $8,500 $10,550 B. At the end of Day 10, the status of the project is as follows. Actual Activity Complete Cost 100% ! $18,000 100% | s23-000 0% D., 10961 $4,000 (a) Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E and the Cost and Schedule variance and the CPI and SPI for the entire project. (b) As project manager, write a brief summary of the status of the project at this time. EV PV Task Comp. Complete BCWP Bcws ACWP Project Totals Page 1
pm 592 homework 6-1 - earned value calculations. please help me find the answer
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started