PM.52 HCA (Hospital Corporations of America) has obtained 5 new hospitals in a recent acquisition. They want to equip these hospitals with state of the

PM.52 HCA (Hospital Corporations of America) has obtained 5 new hospitals in a recent acquisition. They want to equip these hospitals with state of the art cancer treatment equipment and train staff to use it. The company has broken this project down into lettered activities and their durations in weeks:

Activity Duration (weeks) Immediate Predecessor(s)
A 4 -
B 7 A
C 3 A
D 8 B
E 7 B
F 11 C
G 10 D,F
H 14 E
I 11 G
J 2 H,I
K 6 J

What is the overall duration of the project (in weeks)? weeks What is the project's critical path?

ABDGIJK

ACFGIJK

ABEHJK

If activity D were shortened by 2 week(s) and activity G were shortened by 2 week(s), what would be the project's critical path?

ACFGIJK

ABDGIJK

ABEHJK

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Hospitality Law

Authors: Jack P Jefferies, Brown Banks, Banks Brown

4th Edition

0866122273, 9780866122276

More Books

Students also viewed these General Management questions