PM.52 HCA (Hospital Corporations of America) has obtained 5 new hospitals in a recent acquisition. They want to equip these hospitals with state of the art cancer treatment equipment and train staff to use it. The company has broken this project down into lettered activities and their durations in weeks:
Activity | Duration (weeks) | Immediate Predecessor(s) |
---|---|---|
A | 4 | - |
B | 7 | A |
C | 3 | A |
D | 8 | B |
E | 7 | B |
F | 11 | C |
G | 10 | D,F |
H | 14 | E |
I | 11 | G |
J | 2 | H,I |
K | 6 | J |
What is the overall duration of the project (in weeks)? weeks What is the project's critical path?
ABDGIJK | ||
ACFGIJK | ||
ABEHJK |
If activity D were shortened by 2 week(s) and activity G were shortened by 2 week(s), what would be the project's critical path?
ACFGIJK | ||
ABDGIJK | ||
ABEHJK |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started