PM.58 Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination:
PM.58 Tech Solutions XYZ makes accessory products for tablet computers. Below are all the activities required to develop a new wireless keyboard and cover combination: | ||||||
Activity | Duration (days) | Immediate Predecessor(s) | ||||
A | 6 | - | ||||
B | 12 | - | ||||
C | 5 | - | ||||
D | 4 | A | ||||
E | 2 | C | ||||
F | 11 | B,D,E | ||||
G | 15 | D,E | ||||
H | 6 | F | ||||
I | 7 | G,H | ||||
J | 18 | I | ||||
What is the overall duration of the project (in days)? | ||||||
What is theearliestday you couldstartactivity J? (Write the day number in the field below.) | ||||||
What is theearliestday you couldfinishactivity G? | ||||||
What is thelatestday you couldstartactivity C? | ||||||
What is thelatestday you couldfinishactivity B? | ||||||
What is theslacktime for activity D? | ||||||
What would be the overall duration of the project if activity H were increased by 2days, from 7to 9days? |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started