Question

1 Approved Answer

PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4weeksand

PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4weeksand he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.

Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 5 3 $800 $1,200 -
B 6 5 $300 $450 -
C 6 5 $550 $775 -
D 3 2 $900 $1,100 A
E 5 3 $1,350 $1,950 C
F 6 3 $900 $1,200 B

What is the duration of the project (in weeks)?

What is the target duration of the project (after crashing the project)?

By how many weeks should activity A be crashed?

By how many weeks should activity Bbe crashed?

By how many weeks should activity Cbe crashed?

By how many weeks should activity Dbe crashed?

By how many weeks should activity Ebe crashed?

By how many weeks should activity Fbe crashed?

What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)?(Display your answer to two decimal places.)

I just need bottom question answered.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management A Competitive Advantage Approach Concepts

Authors: Fred R. David, Forest R. David

15th edition

978-0133444896, 133444791, 9780133444858, 133444899, 133444856, 978-0133444797

More Books

Students also viewed these General Management questions

Question

Describe why international agreements are difficult.

Answered: 1 week ago

Question

What is the difference between a simple and complex condition ?

Answered: 1 week ago