Question
PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4weeksand
PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4weeksand he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.
Activity | Normal Time (weeks) | Crashed Time (weeks) | Normal Cost | Crashed Cost | Predecessor(s) |
---|---|---|---|---|---|
A | 5 | 3 | $800 | $1,200 | - |
B | 6 | 5 | $300 | $450 | - |
C | 6 | 5 | $550 | $775 | - |
D | 3 | 2 | $900 | $1,100 | A |
E | 5 | 3 | $1,350 | $1,950 | C |
F | 6 | 3 | $900 | $1,200 | B |
What is the duration of the project (in weeks)?
What is the target duration of the project (after crashing the project)?
By how many weeks should activity A be crashed?
By how many weeks should activity Bbe crashed?
By how many weeks should activity Cbe crashed?
By how many weeks should activity Dbe crashed?
By how many weeks should activity Ebe crashed?
By how many weeks should activity Fbe crashed?
What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)?(Display your answer to two decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started