PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4weeksand

PM.61 Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4weeksand he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed.

Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 5 3 $1,000 $1,400 -
B 6 5 $350 $500 -
C 6 5 $550 $675 -
D 3 2 $750 $950 A
E 5 3 $1,500 $2,700 C
F 6 3 $900 $1,200 B

What is the duration of the project (in weeks)?

What is the target duration of the project (after crashing the project)?

By how many weeks should activity A be crashed?

By how many weeks should activity Bbe crashed?

By how many weeks should activity Cbe crashed?

By how many weeks should activity Dbe crashed?

By how many weeks should activity Ebe crashed?

By how many weeks should activity Fbe crashed?

What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)?(Display your answer to two decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Reporting and Analysis

Authors: Flawrence Revsine, Daniel Collins, Bruce, Mittelstaedt, Leon

6th edition

9780077632182, 78025672, 77632184, 978-0078025679

Students also viewed these General Management questions