PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After

PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:

What is the total cost of crashing the project from its current duration down to 13 weeks?

What is the total cost of crashing the project from its original duration to 11 weeks?

Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s)
A 3 2 $1,100 $3,100 -
B 6 5 $2,040 $2,500 -
C 3 2 $1,400 $2,900 -
D 7 3 $2,100 $2,600 A
E 6 3 $1,650 $2,100 B
F 4 2 $4,200 $5,220 C
G 4 2 $1,600 $2,100 D, E

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management In The Hospitality Industry

Authors: Mike Olsen, Michael D Olsen

2nd Edition

0471292397, 9780471292395

More Books

Students also viewed these General Management questions