Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

PMGT 510-52 a figure like Exhibit 10.9, CPT 4e, that illustrates the daily and cumulative costs for the resource-leveled project. the following hourly rates: Alcides

PMGT 510-52

a figure like Exhibit 10.9, CPT 4e, that illustrates the daily and cumulative costs for the resource-leveled project.

the following hourly rates:

Alcides $45 / hr.

Joan $50 / hr.

Activity ID

Activity

Immediate Predecessor

Duration in days

Resource

Work Hours per Day

A

Evaluate freezers

2

Alcides

6

B

Chart temperatures

6

Joan

4

C

Review service record

2

Alcides

D

Consult with HVAC engineer

A, B, C

3

Alcides

E

Develop construction plan

D

10

Joan

F

Complete IC assignment

E

2

Alcides

G

Complete ROI analysis

E

5

Joan

H

Conduct regulatory review

E

4

Joan

I

Obtain construction approval

F, G, H

2

Alcides

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Legal Environment of Business A Critical Thinking Approach

Authors: Nancy K Kubasek, Bartley A Brennan, M Neil Browne

6th Edition

978-0132666688, 132666685, 132664844, 978-0132664844

Students also viewed these Law questions

Question

ints) Evaluate the integral without using a table. re (+ + 1)2

Answered: 1 week ago