Question
PMGT 510-52 a figure like Exhibit 10.9, CPT 4e, that illustrates the daily and cumulative costs for the resource-leveled project. the following hourly rates: Alcides
PMGT 510-52
a figure like Exhibit 10.9, CPT 4e, that illustrates the daily and cumulative costs for the resource-leveled project.
the following hourly rates:
Alcides $45 / hr.
Joan $50 / hr.
Activity ID
Activity
Immediate Predecessor
Duration in days
Resource
Work Hours per Day
A
Evaluate freezers
2
Alcides
6
B
Chart temperatures
6
Joan
4
C
Review service record
2
Alcides
D
Consult with HVAC engineer
A, B, C
3
Alcides
E
Develop construction plan
D
10
Joan
F
Complete IC assignment
E
2
Alcides
G
Complete ROI analysis
E
5
Joan
H
Conduct regulatory review
E
4
Joan
I
Obtain construction approval
F, G, H
2
Alcides
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started