Pogue Ltd had the following information relating to the production of the XLZ240 for June 2022. Budget
Fantastic news! We've Found the answer you've been seeking!
Question:
Pogue Ltd had the following information relating to the production of the XLZ240 for June 2022.
| Budget | Actual | ||
| 12,400 units | 10,800 units | ||
Materials | 68,200kg | 262,570 | 61,700kg | 233,226 |
Direct Labour | 29,149 hours | 253,518 | 24,180 hours | 217,620 |
Fixed Overhead | 332,320 | 318,950 |
Additional information
- Material and labour are variable costs.
- Overheads are fixed costs.
Required:
(a) Calculate and comment on
(i) Material Price variance
(3 marks)
(ii) material usage Variance
(3 marks)
(iii) labour rate variance
(3 marks)
(iv) Labour efficiency variance
(3 marks)
(v) Fixed overhead variance
(3 marks)
(b) Explain the causes of material and labour variance.