points A supplier is late with a delivery which has caused a delay in completion of Derek
Fantastic news! We've Found the answer you've been seeking!
Question:
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/06/665eec8d0b426_972665eec8c4e400.jpg)
![image text in transcribed](https://s3.amazonaws.com/si.experts.images/answers/2024/06/665eec8d48d91_973665eec8d4220a.jpg)
points A supplier is late with a delivery which has caused a delay in completion of Derek and Addison s project In which part of their project status report would Derek and Addison discuss this Problems encountered Project overview Impact on budget The delay should not be mentioned