Popi Limited uses the standard costing system. The standards for Product A are as follows: Material 8 KG at R5.30 per KG Labour 8 Hours
Popi Limited uses the standard costing system.
The standards for Product A are as follows:
- Material 8 KG at R5.30 per KG
- Labour 8 Hours at R100 an hour
- Variable Overheads R40 per labour hour
- Fixed Overheads R50000
- Normal Production 29000 per month
Actual information for the month of May 2021 is:
- Material 182000KG at R6.20 per KG
- Labour 198000 hours at R73 per hour
- Variable overheads R35 per hour of labour
- Fixed overheads R31200
- Production 25000 units
Required
4.2.1 Calculate the material quantity variance. (2 marks)
4.2.2 Calculate the variable manufacturing overhead efficiency variance. (2 marks)
4.2.3 Fixed manufacturing overhead volume variance. (3 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started