Posie Bags (PB) is a designer of high-quality backpacks and purses. Each design is made in small batches. Each spring, PB comes out with new
Posie
Bags (PB) is a designer of high-quality backpacks and purses. Each design is made in small batches. Each spring, PB comes out with new designs for the backpack and the purse. The company uses these designs for a year and then moves on to the next trend. The bags are all made on the same fabrication equipment that is expected to operate at capacity. The equipment must be switched over to a new design and set up to prepare for the production of each new batch of products. When completed, each batch of products is immediately shipped to a wholesaler. Shipping costs vary with the number of shipments. Budgeted information for the year is as follows:
LOADING...
(Click the icon to view the budgeted information.)Read the requirements
LOADING...
.
Requirement 1. Identify the cost hierarchy level for each cost category.
Cost | Cost Hierarchy Level |
Direct materialspurses | Output unit-level cost |
Direct materialsbackpacks | Output unit-level cost |
Direct laborpurses | Output unit-level cost |
Direct laborbackpacks | Output unit-level cost |
Setup | Batch-level cost |
Shipping | Batch-level cost |
Design | Product-sustaining cost |
Plant utilities and administration | Facility-sustaining cost |
Requirement 2. Identify the most appropriate cost driver for each cost category. Explain briefly your choice of cost driver.
Cost | Cost Driver | Reason |
Direct materialspurses | Number of purses |
|
Direct materialsbackpacks | Number of backpacks |
|
Direct laborpurses | Number of purses |
|
Direct laborbackpacks | Number of backpacks |
|
Setup | Number of batches |
|
Shipping | Number of batches |
|
Design | Number of designs |
|
Plant utilities and administration | Hours of production |
|
Choose from any drop-down list and then click Check Answer.
| Clear All | Check Answer
|
Data Table
Posie Bags | |
Budget for Costs and Activities | |
For the Year Ended February 29, 2020 | |
Direct materialspurses | $342,200 |
---|---|
Direct materialsbackpacks | 470,850 |
Direct manufacturing laborpurses | 87,000 |
Direct manufacturing laborbackpacks | 116,100 |
Setup | 90,675 |
Shipping | 71,370 |
Design | 165,000 |
Plant utilities and administration | 221,000 |
Total | $1,564,195 |
Other budget information follows:
| Backpacks | Purses | Total |
---|---|---|---|
Number of bags | 6,450 | 2,900 | 9,350 |
Hours of production | 1,665 | 2,585 | 4,250 |
Number of batches | 115 | 80 | 195 |
Number of designs | 4 | 2 | 6 |
PrintDone
Requirements
1. | Identify the cost hierarchy level for each cost category. |
2. | Identify the most appropriate cost driver for each cost category. Explain briefly your choice of cost driver. |
3. | Calculate the budgeted cost per unit of cost driver for each cost category. |
4. | Calculate the budgeted total costs and cost per unit for each product line. |
5. | Explain how you could use the information in requirement 4 to reduce costs. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started