Question
Power Bhd manufactures electronic scooter, known as T-tech, by purchasing its major switch components, from Luxer Sdn Bhd at a price of RM45 per unit.
Power Bhd manufactures electronic scooter, known as T-tech, by purchasing its major switch components, from Luxer Sdn Bhd at a price of RM45 per unit. Power Bhd also pays the transportation costs of the switch, RM4,000.
Power Bhd will be producing 5,000 units of T-tech for the coming year and is considering
making the controller internally.
The costs to produce one unit of the controller are as follow:
Direct materials RM12
Direct labour (RM4 per hour) RM10
Production overhead (applied based on direct labour hour) RM17
Additional costs of RM12,000 will be incurred by Power Bhd to check and monitor the
production process if the switch is produced internally.
The materials used to make the switch are currently being used to make another product, a
robotic toy. Materials required to make each switch is 1 kg whilst to make each robotic toy
requires 2.5 kg materials. Materials are in short supply and a total of 6000 kg would be
available for the coming year.
The following data relate to the selling price and costs for one unit of robotic toy:
Selling price RM 100
Direct materials RM 36
Direct labour (RM4 per hour) RM 20
Production overhead (applied based on direct labour hour) RM 34
The anticipated production for the year is 20,000 direct labour hours. Fixed production overhead for the year is budgeted at RM96,000. Production overheads are absorbed based
on direct labour hour.
Required:
a) Compute the opportunity cost if Power Bhd decides to manufacture the switch.
(4 marks)
b) Compute the relevant cost of making and relevant cost of buying the switch.
(5 marks)
c) Compare and select the best decision based on your answer on (b) above (2 marks)
d) List TWO (2) qualitative factors in order to make or buy decision (4 marks)
(Total :15 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
a Opportunity Cost of Manufacturing the Switch The opportunity cost represents the value of the next best alternative foregone when a decision is made ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started