Question
Poweron Construction Company commences the construction of a museum on 1 July 2018. It signs a fixed-price contract for total revenue of $190 million. The
Poweron Construction Company commences the construction of a museum on 1 July 2018. It signs a fixed-price contract for total revenue of $190 million. The project is expected to be completed by the end of June 2021. The expected cost at the commencement of construction was $170 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project:
2019 | 2020 | 2021 | |
($ M) | ($ M) | ($ M) | |
Costs for the year | 50 | 60 | 50 |
Costs incurred to date | 50 | 110 | 160 |
Estimated costs to complete | 120 | 60 | - |
Progress billings during the year | 40 | 80 | 70 |
Cash collected during the year | 35 | 80 | 75 |
The contract is completed as expected on 30 June 2021. Poweron Construction Company uses the percentage-of-completion method to account for its construction contract.
REQUIRED
a. Compute the gross profit to be recognised for each of the three years.
b. Provide the journal entries for each year. Assume the stage of completion can be reliably determined. Exclude journal narrations.
c. Prepare the journal entries for each year assuming the stage of completion and the outcome of the construction contract cannot be reliably estimated. Show the differences from b) only. Exclude journal narrations.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started