Question
PPL, Inc. produces high-quality but expensive training shoes for runners. Manufacturing the shoes requires ten separate tasks. There are 400 minutes available for manufacturing the
PPL, Inc. produces high-quality but expensive training shoes for runners. Manufacturing the shoes requires ten separate tasks. There are 400 minutes available for manufacturing the shoes in the plant daily. Daily demand is 60. The information for tasks is as follows:
a) What is the theoretical workstation cycle time?
b) Balance the line by using the Ranked positional weight. And use longest operation time as a secondary criterion. Finally, write the sequence of each task in each workstation.
c) What is the efficiency of your line balance? What is the total idle time?
d) which Workstation(s) is(are) the bottleneck of the system?
\begin{tabular}{|c|c|c|c|c|c|} \hline Task & Task Time (min) & Immediate Predecessor & Task & Task Time (min) & Immediate Predecessor \\ \hline A & 1 & & F & 3 & A \\ \hline B & 4 & A & G & 2 & F \\ \hline C & 2 & B & H & 5 & G \\ \hline D & 4 & B & I & 1 & E,II \\ \hline E & 1 & C,D & J & 3 & I \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|} \hline Task & Task Time (min) & Immediate Predecessor & Task & Task Time (min) & Immediate Predecessor \\ \hline A & 1 & & F & 3 & A \\ \hline B & 4 & A & G & 2 & F \\ \hline C & 2 & B & H & 5 & G \\ \hline D & 4 & B & I & 1 & E,II \\ \hline E & 1 & C,D & J & 3 & I \\ \hline \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started