Prepare a cash flow forecast in a tabular form with reference to the following information: Contract Sum for Main Contract Works: AUD$200,000,000 including a

Prepare a cash flow forecast in a tabular form with reference to the following information:

 Contract Sum for Main Contract Works: AUD$200,000,000 including a Provisional Sum of AUD $10,000,000 for Contingencies and Prime Cost Sum of AUD $40,000,000 for Nominated Sub-Contract M&E works and

 Contract Period – Main contract: 25 months  Contract Period – Sub-Contract M&E works: 18 months (Start from Month 8 of the main Contract Period)

 Retention: 10% (but up to 5% of the total contract sum)

 One moiety of the retention to be released to be released at the date of practical completion

 Another half of the retention shall be released upon the expiry of the Defects Liability Period (say 12 months after the practical completion of the Work)

Step by Step Solution

3.40 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

Main Contract incl Contingencies AUD 200000000 5 of total contract Sum Nominated SubContract ME AUD ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

John E Freunds Mathematical Statistics With Applications

Authors: Irwin Miller, Marylees Miller

8th Edition

978-0321807090, 032180709X, 978-0134995373

More Books

Students also viewed these Finance questions

Question

How much is $102 after a decrease of 100%?

Answered: 1 week ago

Question

Calculate the missing value.

Answered: 1 week ago