Question
1 Approved Answer
Prepare a master production schedule based on the following information: Week: 1 2 3 4 5 6 7 8 Forecast 100 100 120 120 150
Prepare a master production schedule based on the following information:
Week: | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Forecast | 100 | 100 | 120 | 120 | 150 | 150 | 160 | 180 |
Orders | 106 | 94 | 65 | 40 | 21 | 9 | 2 | 0 |
Beginning inventory: 150 Schedule production whenever projected-on-hand drops below 20. The production lot size is 250 units. What is the difference between the Available to Promise Inventory and the Projected On Hand Inventory) for Period 7?