Prepare a Master Production Schedule (MPS) for an Agri-Chemical company given the following information: The forecast for each week of an eight week schedule is
Prepare a Master Production Schedule (MPS) for an Agri-Chemical company given the following information: The forecast for each week of an eight week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows: Week Customer Orders 1 52 2 35 3 20 4 12 Use a production lot size of 75 units and no beginning inventory