Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows. Week Customer Orders 1 52 2 35 3 20 4 12 Use a production lot size of 75 units and no beginning inventory. litinn for each period for Problem 21. Chapter 11 problem 21 Prepare a master schedule like that shown in Figure 11.11, in which weeks do we need to make production? The MPs rule is to schedule production of the projected on-hand Inventory would be negative without it. 2 3 5 6 7 8 QUESTION 13 Chapter 11, problem 21 Prepare a master schedule like that shown in Figure 11.11. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. What is the projected on-hand inventory by the end of week 47 23 Prepare a master schedule like that shown in Figure 11.11 given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows. Week Customer Orders 1 52 2 35 3 20 4 12 Use a production lot size of 75 units and no beginning inventory. litinn for each period for Problem 21. Chapter 11 problem 21 Prepare a master schedule like that shown in Figure 11.11, in which weeks do we need to make production? The MPs rule is to schedule production of the projected on-hand Inventory would be negative without it. 2 3 5 6 7 8 QUESTION 13 Chapter 11, problem 21 Prepare a master schedule like that shown in Figure 11.11. The MPS rule is to schedule production if the projected on-hand Inventory would be negative without it. What is the projected on-hand inventory by the end of week 47 23