Prepare cost sheet of the following data. Raw materials consumed Rs. 80,000 Direct wages Rs. 48,000 Machine hours worked 8,000 Hours Machine hour rate Rs.

Prepare cost sheet of the following data.

Raw materials consumed Rs. 80,000

Direct wages Rs. 48,000

Machine hours worked 8,000 Hours

Machine hour rate Rs. 4

Office overhead 10% of works cost

Selling overhead Rs. 1.50 per unit

Units produced 4000 units

Units sold 3600 units at Rs 50 each.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Accounting

Authors: Floyd A. Beams, Joseph H. Anthony, Bruce Bettinghaus, Kenneth Smith

11th Edition

978-0132568968, 9780132568968

More Books

Students also viewed these Accounting questions