Question

1 Approved Answer

Prepare Interim Certificate No. 3 in the prescribed format. Calculate the payment due to the main contractor for that particular month. You must show detailed

Prepare Interim Certificate No. 3 in the prescribed format. Calculate the payment due to the main contractor for that particular month. You must show detailed workings, where necessary. Works completed to date

Variation works (Nett addition) $ 100,000 Reinforced concrete work $ 150,000 Structural steelwork $ 300,000 Sanitary and plumbing works $ 30,000 Other information Contract sum $ 5,000,000 Deposit paid to supplier $ 20,000 Pest control services $ 2,500 Rental of vehicles for site staff $ 15,000 Total payment paid to main contractor $ 200,000 Materials delivered to site $ 50,000 Material ordered but not delivered to site $ 80,000 Limit of retention 5% of Contract sum

Retention for work done As per Public Sector Standard Conditions of Contract (PSSCOC) under the building and construction Authority (BCA) Singapore Retention for unfixed material As per PSSCOC

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David Kroenke

2nd Edition

0136078680, 9780136078685

More Books

Students also viewed these General Management questions

Question

Is there anything else you would like us to know about you?

Answered: 1 week ago