Question
Prepare Interim Certificate No. 3 in the prescribed format. Calculate the payment due to the main contractor for that particular month. You must show detailed
Prepare Interim Certificate No. 3 in the prescribed format. Calculate the payment due to the main contractor for that particular month. You must show detailed workings, where necessary. Works completed to date
Variation works (Nett addition) $ 100,000 Reinforced concrete work $ 150,000 Structural steelwork $ 300,000 Sanitary and plumbing works $ 30,000 Other information Contract sum $ 5,000,000 Deposit paid to supplier $ 20,000 Pest control services $ 2,500 Rental of vehicles for site staff $ 15,000 Total payment paid to main contractor $ 200,000 Materials delivered to site $ 50,000 Material ordered but not delivered to site $ 80,000 Limit of retention 5% of Contract sum
Retention for work done As per Public Sector Standard Conditions of Contract (PSSCOC) under the building and construction Authority (BCA) Singapore Retention for unfixed material As per PSSCOC
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started