Question
Presently demand exceeds capacity and Apex has capacity constraints. There are three production lines that operate 24 hours a day for 360 days per year
Presently demand exceeds capacity and Apex has capacity constraints. There are three production lines that operate 24 hours a day for 360 days per year (25,920 hours), which leaves fives days a year for maintenance. All three products go through the same work centres in roughly the same sequence. Some work centres create bottlenecks since they have less capacity than other centres
Demand (in units) ,Revenue Variable, costs Allocated fixed costs, Operating income, Time in production (minutes).
Product A 100.000 $150 $80 $60 $10 4
Product B 300,000 $85 $40 $25 $20 3
Product C 500,000 $55 $15 $25 $15 2
Required:
1) Recommend how to maximize profits by calculating the optimal product mix. State how many of each product should Apex produce?
2) What should Apex do to better manage the constrained production centres?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Answer To maximize profits Apex should focus on producing the most profitable product mix given the production capacity constraints 1 Calculating the ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3