President of Gentech Construction, has developed the tasks, duration, and predecessor relationship for his new project in the following table ( times in weeks )
President of Gentech Construction, has developed the tasks, duration, and predecessor relationship for his new project in the following table times in weeks:
tableActivitytableImmediatePredecessortableOptimisticweekstableMost LikelyweekstablePessimisticweeksABACADAEBFECGECHFIFJDGHKI,J
Calculate the expected activity time and the variance for all activities.
Draw a project network AON and find ES EF LS and LF time for each activity.
What is the completion time and the critical path of the project?
What is the probability that the project will be completed before a weeks deadline?
What is the probability that the project will be completed before a weeks deadline?
What should be the deadline of the project if the probability to finish within that time frame would be
P
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started