President of Gentech Construction, has developed the tasks, duration, and predecessor relationship for his new project in the following table ( times in weeks )

President of Gentech Construction, has developed the tasks, duration, and predecessor relationship for his new project in the following table (times in weeks):
\table[[Activity,\table[[Immediate],[Predecessor]],\table[[Optimistic],[(weeks)]],\table[[Most Likely],[(weeks)]],\table[[Pessimistic],[(weeks)]]],[A,-,4,8,12],[B,A,10,15,26],[C,A,8,12,16],[D,A,4,6,14],[E,B,1,2,3],[F,E,C,4,7,10],[G,E,C,2,3,4],[H,F,2,2,2],[I,F,6,6,6],[J,D,G,H,3,6,15],[K,I,J,6,7,8]]
Calculate the expected activity time and the variance for all activities.
Draw a project network (AON) and find ES, EF, LS and LF time for each activity.
What is the completion time and the critical path of the project?
What is the probability that the project will be completed before a 52 weeks dead-line?
What is the probability that the project will be completed before a 42 weeks dead-line?
What should be the dead-line of the project if the probability to finish within that time frame would be 90%?
P3-2
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions

Question

Explain the term benchmarking and its benefits.

Answered: 1 week ago