Price out a proposed change for an added foundation raft slab underneath the elevator shaft with the dimensions of 20mx12mx1m. Actual cost of Labour is
Price out a proposed change for an added foundation raft slab underneath the elevator shaft with the dimensions of 20mx12mx1m. Actual cost of Labour is $ 46,000, material is $32,000 and equipment is $7,000 for the changed work. Assume contractor overhead is 10% and profit is 6% for the markup. Calculate the price of the change order of the above change using Method 2. Question 26 options: a. $99,110 b. $99,150 d. $98,115 c. $98,260