Privett, Inc. purchased land in 2019. An existing structure was demolished, and a new warehouse was constructed on the property in September of 2019. Privett
- Privett, Inc. purchased land in 2019. An existing structure was demolished, and a new warehouse was constructed on the property in September of 2019. Privett hired construction workers at a rate of $25 per hour to do the work (1,680 hours in total). Privetts operations manager spent 25% of his time in September supervising the construction.
Warehouse Construction Cost Data | |||
Purchase price Land | $125,000 | Cost to remove structure on land | $10,000 |
Operation managers monthly salary | 5,000 | Proceeds from sale of metal from demolished structure | 3,000 |
Paving of parking lot | 10,000 | Landscaping costs | 12,000 |
Foundation work | 15,000 | Direct materials Warehouse | 105,000 |
Parking lot lighting | 10,000 | Closing costs on land purchase | 5,000 |
Electrical/Plumbing contractors | 25,000 | ||
Hourly wage rate Workers | 25 | Payroll tax rate (all employees) | 10% |
Privett had an appraisal done in October 2019. The land and land improvements were appraised for $150,000 and $50,000, respectively; the building was appraised for $175,000.
What is the cost of the warehouse project recorded on the books?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started