Question

1 Approved Answer

Problem 0 3 ( from an old exam ) : For the chemical production of A and B , it is scheduled to produce the

Problem 03(from an old exam):
For the chemical production of A and B, it is scheduled to produce the same number of batches
for A and B.
Below is a Table that summarizes their processing time (in hr).
Step 01 Step 02 Step 03 Step 04 Density
A 2.51.54.550.9 kg/L
B 3.53.55.541 kg/L
a) Assume that each product will be produced in separate campaigns (AAA...BBB...), and
there is NO OVERLAP between campaigns (that is, step 01 for product B cannot start
before step 04 of product A).
Determine the number of batches for each product (A and B) required each month
(makespan per month =600h) in these two separate scenarios:
a.1 Assuming a non-overlapping policy. Answer: # batches A = # batches B =______
a.2 Assuming a Zero wait policy. Answer: # batches A = # batches B =______
b) From part a2(zero-wait policy), if the yearly demand for product B is 180,000 kg/year,
determine the storage capacity (volume) for this product B assuming constant demand for
B.
Answer: Storage volume for product B =_________liters

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Process

Authors: Lee Long

4th Edition

978-0201822939,0201822938

More Books

Students also viewed these General Management questions

Question

What is the conclusion of the ANOVA F-test in plain English?

Answered: 1 week ago

Question

fscanf retums a special value EOF that stands for...

Answered: 1 week ago