Problem 1 3 - 1 6 ( Static ) A company produces two very similar products that go through a three - step sequence of

Problem 13-16(Static)
A company produces two very similar products that go through a three-step sequence of fabrication, assembly, and packaging. Each step requires one day for a lot to be completely processed and moved to the next department. Processing requirements for the departments (hours per unit) are
FABRICATION ASSEMBLY PACKAGING
Product Labor Machine Labor Machine Labor Machine
A 211.511.5
B 11111.5.5
Department capacities are all 700 hours of labor and 500 hours of machine time, except Friday, when capacities are 200 hours for both labor and machine time. The following production schedule is for next week:
Units scheduled to be produced
Product Mon Tues Wed Thurs Fri
A 200400100300100
B 300200200200200
Click here for the Excel Data File
Develop a production schedule for each department that shows the capacity requirements for each product and the total load for each day. Ignore changeover time. Note: The Load of Labor and Machine may exceed the Capacity. (Round your answers to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Emergency Management

Authors: Jane A Bullock, George D Haddow

7th Edition

0128171391, 9780128171394

More Books

Students also viewed these General Management questions

Question

1. Why do we trust one type of information more than another?

Answered: 1 week ago