Problem 1 6 - 1 4 ( Static ) The production manager must determine the processing sequence for seven jobs through the grinding and then

Problem 16-14(Static)
The production manager must determine the processing sequence for seven jobs through the grinding and then deburring departments. The same sequence will be followed in both departments. The managers goal is to move the jobs through the two departments as quickly as possible. The foreman of the deburring department wants the SPT rule to be used to minimize the work-in-process inventory in his department.
PROCESSING TIME
(hours)
Job Grinding Deburring
A 36
B 24
C 15
D 43
E 94
F 87
G 62
Click here for the Excel Data File
a. Prepare a schedule using SPT for the grinding department.
b-1. What is the total flow time in the grinding department for the SPT sequence?
b-2. What is the makespan to process the seven jobs in both the grinding and deburring departments?
c-1. Determine a sequence that will minimize the total time needed to process the jobs in both departments.
c-2. What total flow time will result for the grinding department?
c-3. What is the makespan to process the seven jobs in both the grinding and deburring department, based on your job order in c-1?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Project Management Made Simple

Authors: Terry Schmidt

2nd Edition

1119718171, 978-1119718178

More Books

Students also viewed these General Management questions