Problem 1: Consider the following set of processes: Process Arrival Time (s) Processing Time (s) A 0 3 B 1 5 C 3 2 D
Problem 1: Consider the following set of processes:
Process | Arrival Time (s) | Processing Time (s) |
A | 0 | 3 |
B | 1 | 5 |
C | 3 | 2 |
D | 9 | 5 |
E | 12 | 5 |
Calculate the start and finish times of each of the processes using the following scheduling algorithms: HRRN.