Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem 1 Consider the following tasks for a project. Task Time (Days) Immediate Predecessors A 3 - B 2 A C 6 A D 2

Problem 1 Consider the following tasks for a project.

Task Time (Days)

Immediate

Predecessors

A 3 -
B 2 A
C 6 A
D 2 C
E 3 A
F 3 B
G 5 C
H 1 C
I 1.5 F,H
J 2 I

(a) Draw the project network and determine the critical path(s) using AOA method and determine the critical path. (b) The project manager felt that CPM should not be used for this project. Instead, the best, worst and most likely time was estimated for each activity and PERT was used. The time to complete the project had a mean of 18.5 days and a standard deviation of 2.15 days. (i) Determine the probability that is will take more than 20 days to finish the project. (ii) The project manager wants to tell the client he is 90% sure the project will be completed by time X. What is the value of X?

Problem 2 Draw project network from Problem 1 using AON method, filling the ES, EF, LS, LF and slack for each node.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Information Technology

Authors: Carol Brown, Daniel DeHayes, Jeffrey Hoffer, Wainright Marti

7th Edition

132146320, 978-0132146326

More Books

Students also viewed these General Management questions

Question

Evaluate 3x - 1 / x - 1. lim

Answered: 1 week ago

Question

Outline five major criticisms of humanistic psychologies.

Answered: 1 week ago