John, a cost analyst for a manufacturing firm, was asked to estimate the overhead costs at one of the factories. He interviewed the supervisor and several workers there to get a feel of how overhead costs changed. His experience with the cost accounting system pointed to the use of machine hours as the cost driver for overhead items.
Over the last 12 months, the total overhead costs were $103,918. John determined that total fixed overhead costs totaled $4,620 per month; the rest are variable costs. For the same period of time, 4,519 machine hours were incurred in that factory.
Required:
- What is the general cost equation (TC = F + VX) that describes the relation between overhead costs and machine hours?
- If the factory expects to spend 400 machine hours next month, what is the expected amount of overhead costs?
Problem 2
(Continued from Problem 1)
John, a cost analyst for a manufacturing firm, was asked to estimate the overhead costs at one of the factories. He interviewed the supervisor and several workers there to get a feel of how overhead costs changed. His experience with the cost accounting system pointed to the use of machine hours as the cost driver for overhead items. Over the last 12 months, the total overhead costs were $103,918, out of which John determined $4,620 to be fixed cost per month and the rest variable cost. For the same period of time, 4,519 machine hours were incurred in that factory.
The cost analyst, John, went back to the accounting information system to look for more relevant data. The following breakdown of the overhead costs and the associated machine hours over the same 12-month period was available:
Month | Overhead | Machine Hours |
1 | $ 7,102 | 203 |
2 | 8,620 | 319 |
3 | 9,120 | 425 |
4 | 7,092 | 289 |
5 | 7,965 | 388 |
6 | 9,641 | 471 |
7 | 10,421 | 512 |
8 | 8,834 | 443 |
9 | 6,935 | 262 |
10 | 8,520 | 371 |
11 | 10,342 | 494 |
12 | 9,326 | 342 |
Total | $103,918 | 4,519 |
|
|
|
Required:
- Plot the data using scattergraph.
- Use the high-low method to estimate the cost function.
- Predict overhead costs when 400 machine hours are expected to be spent for the coming month.
Problem 3
(Continued from Problem 2)
John, a cost analyst for a manufacturing firm, was asked to estimate the overhead costs at one of the factories. He interviewed the supervisor and several workers there to get a feel of how overhead costs changed. His experience with the cost accounting system pointed to the use of machine hours as the cost driver for overhead items. Over the last 12 months, the total overhead costs were $103,918, out of which John determined $4,620 to be fixed cost per month and the rest variable cost. For the same period of time, 4,519 machine hours were incurred in that factory.
The cost analyst, John, went back to the accounting information system to look for more relevant data. The following breakdown of the overhead costs and the associated machine hours over the same 12-month period was available:
Month | Overhead | Machine Hours |
1 | $ 7,102 | 203 |
2 | 8,620 | 319 |
3 | 9,120 | 425 |
4 | 7,092 | 289 |
5 | 7,965 | 388 |
6 | 9,641 | 471 |
7 | 10,421 | 512 |
8 | 8,834 | 443 |
9 | 6,935 | 262 |
10 | 8,520 | 371 |
11 | 10,342 | 494 |
12 | 9,326 | 342 |
Total | $103,918 | 4,519 |
|
|
|
John recently attended a workshop on statistical analysis. He was interested in applying the regression analysis to solve the relation between overhead costs and machine hours.
Required:
- Determine the cost equation using the regression analysis and interpret the regression results.
- Predict overhead costs when 400 machine hours are expected to be spent for next month.
- Indicate the t-statistic and the p-value associated with the estimated coefficient, b.
- Given a t value of 2.228, construct the 95 percent confidence interval around the estimated coefficient, b.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started