Problem 1 Please perform the forward pass and backward pass for the list of activities shown below and find out the ESD, EFD, LSD ,
Problem
Please perform the forward pass and backward pass for the list of activities shown below and find out the ESD, EFD, LSD LFD for all the activities in the network. Put the information in the appropriate locations in each of the activity nodes DO NOT calculate any float
tableActivity List for Reroofing Project,Duration Days,PredecessorsActivity Description,A Move inAB Set up scaffolds,BC Tear off old shingles,C SSD Inspect roof truss and deck,C FFE Remove old shingles to recycling yard,AF Purchase new shingles,C D FG Install new shingles,GH Clean upHI Move out,,
"Under Predecessors, the following notation is used:
x#: ctivity x must finish # days before this activity can begin.
#: The # of days after activity starts that this activity can begin.
#: This activity cannot finish until # days after is completed.
#: This activity must finish # days before can start.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started