Problem 1: Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you

Problem 1: Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the adjusted total cost. Act. A abo - kh khi B C F Crash Cost (Slope) 0 100 50 A 1x 60 70 90 Maximum Crash Time 0 2 1 1 2 1 15 E w+ 3 Normal Time 1 3 4 3 4 3 Initial project duration 12 Total direct cost $ Normal Cost 100 150 200 200 200 150 Problem 2: Teloxy Engineering has received a onetime contract to design and build 10,000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. One of the ingredients necessary to build the product was a small component that could be purchased for $60 in the marketplace, including quantity discounts. Accordingly, management budgeted $650,000 for the purchasing and handling of 10,000 components plus scrap. During the design stage, your engineering team informs you that the final design will require a somewhat higher-grade component that sells for $72 with quantity discounts. The new price is substantially higher than you had budgeted for. This will create a cost overrun. You meet with your manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. Your manufacturing team informs you that they can produce a maximum of 10,000 units, just enough to fulfill your contract. The setup cost will be $100,000 and the raw material cost is $40 per component. Since Teloxy has never manufactured this product before, manufacturing expects the following defects: % defective 0 Probability of occurrence (%) 10 10 20 20 30 30 25 40 15 All defective parts must be removed and repaired at a cost of $120 per part. 1. Using expected value, is it economically better to make or buy the component? 2. Strategically thinking, why might management opt for other than the most economical choice?

Step by Step Solution

3.47 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

ANSWER In this network there are two paths These two paths and their respective lengths are listed b... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these Accounting questions

Question

Why is intrinsic motivation healthier than extrinsic motivation?

Answered: 1 week ago

Question

What is the difference between free slack and total slack?

Answered: 1 week ago