Problem 1. You are completing a project to design a Miami, Florida swimming pool. The contract is a cost plus incentive fee contract. The target

Problem 1. You are completing a project to design a Miami, Florida swimming pool. The contract is a cost plus incentive fee contract. The target costs are $300,000, with a 10-percent target profit. However, the project came in at $275,000. The incentive split is 80/20. How much will the total contract cost? Show all work!

Problem 2. A buyer negotiates a fixed price incentive contract with the seller. The target cost is $200,000, the target profit is $35,000, and the target price is $250,000. The buyer negotiates a ceiling price of $280,000 and a share ratio of 70/30. If the contract is completed with actual costs of $180,000, how much profit will the buyer pay the seller? Show all

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Strategic Management

Authors: J. Hunger, Thomas Wheelen

5th Edition

0136006698, 9788120348615

More Books

Students also viewed these General Management questions

Question

1. What does this mean for me?

Answered: 1 week ago