Problem #1 You have a construction project that requires 12,000 man-hours at a rate of $60 per hour. The estimated duration of the project is
Problem #1
You have a construction project that requires 12,000 man-hours at a rate of $60 per hour. The estimated duration of the project is 7 months and the total cost of the materials was estimated at $250,000. The scheduled percent complete (PC) of the work and the material consumption for each month is as follows:
Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
Monthly Scheduled PC | 10% | 10% | 20% | 25% | 15% | 15% | 5% |
This means on month 1, 10% of the work and materials is supposed to be used, on month 2 another 10% and so on and on.
At the end of month #5, earned value analysis is performed and it is found that only 35% of the work has been completed. The other available information is as follows:
- 60% of the man-hours were spent by the end of the 5th month.
- 40% of the materials were consumed by the end of the 5th month.
- A change order estimated at $30,000 was issued and approved at the end of month # 6.
- The material costs escalated by 35% after the 5th month.
- 30% of the cost of material consumed by the end of the 4th month was escalated by 20%.
Using the above-mentioned information, calculate the following:
- Original BAC
- BCWS
- BCWP
- ACWP
- SV
- CV
- DCWP
- Expenditure variance
- SPI
- EAC considering the same rate of progress
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started