Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem #1 You have a construction project that requires 12,000 man-hours at a rate of $60 per hour. The estimated duration of the project is

Problem #1

You have a construction project that requires 12,000 man-hours at a rate of $60 per hour. The estimated duration of the project is 7 months and the total cost of the materials was estimated at $250,000. The scheduled percent complete (PC) of the work and the material consumption for each month is as follows:

Month

1

2

3

4

5

6

7

Monthly Scheduled PC

10%

10%

20%

25%

15%

15%

5%

This means on month 1, 10% of the work and materials is supposed to be used, on month 2 another 10% and so on and on.

At the end of month #5, earned value analysis is performed and it is found that only 35% of the work has been completed. The other available information is as follows:

  • 60% of the man-hours were spent by the end of the 5th month.
  • 40% of the materials were consumed by the end of the 5th month.
  • A change order estimated at $30,000 was issued and approved at the end of month # 6.
  • The material costs escalated by 35% after the 5th month.
  • 30% of the cost of material consumed by the end of the 4th month was escalated by 20%.

Using the above-mentioned information, calculate the following:

  1. Original BAC
  2. BCWS
  3. BCWP
  4. ACWP
  5. SV
  6. CV
  7. DCWP
  8. Expenditure variance
  9. SPI
  10. EAC considering the same rate of progress

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Theory

Authors: Ahmed Raihi-Belkaoui

5th Edition

1844800296, 978-1844800292

More Books

Students also viewed these Accounting questions