Problem 11-7 SummerFun, Inc., produces a variety of recreation and leisure products. The production manager has developed an aggregate forecast: Month Mar Apr May Jun

Problem 11-7

SummerFun, Inc., produces a variety of recreation and leisure products. The production manager has developed an aggregate forecast:

Month Mar Apr May Jun Jul Aug Sep Total
Forecast 50 44 55 60 50 40 51 350

Use the following information to develop aggregate plans.

Regular production cost $ 80 per unit Back-order cost $20 per unit
Overtime production cost $ 120 per unit Beginning inventory 0 units
Regular capacity 40 units per month
Overtime capacity 8 units per month
Subcontracting cost $ 140 per unit
Subcontracting capacity 12 units per month
Holding cost $ 10 per unit per month

1.

Develop an aggregate plan using each of the following guidelines and compute the total cost for each plan.

a.

Use regular production. Supplement using inventory, overtime, and subcontracting as needed. No backlogs allowed. (Round your Average values to 1 decimal place. Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)

Period Mar Apr May Jun Jul Aug Sep Total
Forecast 50 44 55 60 50 40 51 350
Output
Regular
Overtime
Subcontract
Output - Forecast
Inventory
Beginning
Ending
Average
Backlog

Costs:
Regular $ $
Overtime
Subcontract
Inventory

Total $ $

b.

Develop aggregate plan using the same strategy used in part a except that backlogs are allowed here. There should be no backlog remaining at the end of September. Hint: Use a maximum backlog of 5 in any given month. You will need to develop a set of rules regarding which capacity option (regular, overtime, subcontracting) is always preferable, and regarding the timing of these options (i.e., is it cost-effective to build ahead (and thus carry inventory) or to incur a backlog?). (Round your Average values to 1 decimal place. Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)

Period Mar Apr May Jun Jul Aug Sep Total
Forecast 50 44 55 60 50 40 51 350
Output
Regular
Overtime
Subcontract
Output - Forecast
Inventory
Beginning
Ending
Average
Backlog

Costs:
Regular $ $
Overtime
Subcontract
Inventory
Backlog

Total $ $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions