Problem 13-13 (Algorithmic) Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic
Problem 13-13 (Algorithmic)
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:
Activity | Optimistic | Most Probable | Pessimistic |
A | 5 | 6 | 7 |
B | 3.5 | 4 | 4.5 |
C | 6 | 7 | 8 |
D | 5 | 6 | 9 |
E | 6.5 | 8 | 9 |
F | 2 | 3 | 4 |
G | 8 | 9 | 12 |
H | 6 | 7 | 12 |
What is the probability that the project will be completed. If required, round your answers to four decimal places.
Within 21 weeks?
Within 23 weeks?
Within 25 weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started