Problem 14.35 Quality Cost Report, Interim Performance Report Recently, Ulrich Company received a report from an external consulting group on its quality costs. The consultants
Problem 14.35 Quality Cost Report, Interim Performance Report
Recently, Ulrich Company received a report from an external consulting group on its quality costs. The consultants reported that the company's quality costs total about 21 percent of its sales revenues. Somewhat shocked by the magnitude of the costs, Rob Rustin, president of Ulrich Company, decided to launch a major quality improvement program. For the coming year, management decided to reduce quality costs to 17 percent of sales revenues. Although the amount of reduction was ambitious, most company officials believed that the goal could be realized. To improve the monitoring of the quality improvement program, Rob directed Pamela Golding, the controller, to prepare monthly performance reports comparing budgeted and actual quality costs. Budgeted costs and sales for the first two months of the year are as follows:
January | February | |||
Sales | $ 500,000 | $ 600,000 | ||
Quality costs: | ||||
Warranty | $ 15,000 | $ 18,000 | ||
Scrap | 10,000 | 12,000 | ||
Incoming materials inspection | 2,500 | 2,500 | ||
Product acceptance | 13,000 | 15,000 | ||
Quality planning | 2,000 | 2,000 | ||
Field inspection | 12,000 | 14,000 | ||
Retesting | 6,000 | 7,200 | ||
Allowances | 7,500 | 9,000 | ||
New product review | 500 | 500 | ||
Rework | 9,000 | 10,800 | ||
Complaint adjustment | 2,500 | 2,500 | ||
Downtime (defective parts) | 5,000 | 6,000 | ||
Quality training | 1,000 | 1,000 | ||
Total budgeted costs | $ 86,000 | $100,500 | ||
Quality cost-to-sales ratio | 17.20 | % | 16.75 | % |
The following actual sales and actual quality costs were reported for January:
Sales | $ 550,000 | |
Quality costs: | ||
Warranty | 17,500 | |
Scrap | 12,500 | |
Incoming materials inspection | 2,500 | |
Product acceptance | 14,000 | |
Quality planning | 2,500 | |
Field inspection | 14,000 | |
Retesting | 7,000 | |
Allowances | 8,500 | |
New product review | 700 | |
Rework | 11,000 | |
Complaint adjustment | 2,500 | |
Downtime (defective parts) | 5,500 | |
Quality training | 1,000
|
1. Reorganize the monthly budgets so that quality costs are grouped in one of four categories: appraisal, prevention, internal failure, or external failure. (Essentially, prepare a budgeted cost of quality report.) Also, identify each cost as variable (V) or fixed (F). (Assume that no costs are mixed.)
january | february | |
prevention costs: | ||
quality planning | ||
new product review | ||
quality training | ||
total prevention costs | ||
appraisal costs: | ||
material inspection | ||
product acceptance | ||
field inspection | ||
total appraisal costs | ||
internal failure costs: | ||
scrap | ||
retesting | ||
rework | ||
downtown | ||
total internal failure costs | ||
external failure costs: | ||
warranty | ||
allowance | ||
complaint adjustment | ||
total external failure costs | ||
total quality costs |
2. Prepare a performance report for January that compares actual costs with budgeted costs. If an amount is zero, enter "0". If variance amount is unfavorable enter "U" and enter "F", if it is Favorable. If there is no variance, enter "NA". All values should be entered as positive.
actual costs | budgeted costs | budget variance | ||
prevention costs: | ||||
quality planning | ||||
new product review | ||||
quality training | ||||
total prevention costs | ||||
appraisal costs: | ||||
material inspection | ||||
product acceptance | ||||
field inspection | ||||
total appraisal costs | ||||
internal failure costs: | ||||
scrap | ||||
retesting | ||||
rework | ||||
downtown | ||||
total internal failure costs | ||||
external failure costs: | ||||
warranty | ||||
allowance | ||||
complaint adjustment | ||||
total external failure costs | ||||
total quality costs |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started