Problem 14.9 The demand for subassembly Sis 9 units in week 7. Each unit of requires 2 unts of and 1 unit of U. Each unt of requires 1 unt of 1 unit of W. and 2 units of X. Finally, each unit of requires 1 unt of Y and 2 unts of Z One firm mandatures all items. It takes 2 weeks to make S. 1 week to make T, 2 weeks to make u. 2 weeks to make V. 3 weeks to make W. 1 week to make X 2 weeks to make and 1 week to make 2 Click the icon to view the product structure and the time phased product structure TE Click the icon to view the on hand inventory Suppose that in addition to 90 units of S. there is a demand for 20 unts of which is a component of The 20 units of Ure reeded for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for sounds of due in week 8. Modify the mill requirements plan to reflect these changes Construct a new material requirements plan enter your responses a whole numbers Item Week Lead Time 1. 2 3 6 7 & 5 Gross reg On hand Netre 2 Onder recept Order release 4 5 Enter your answer in the edit fields and then click Check Answer 7 remaining core: 0 of 1 pt 6 of 14 (9 complete) HW Score: 44.5%, 6.23 of Question Help Problem 14.9 -X of The demand for subassembly S is 90 units in week 7. Each unit of requires 2 units of T and 1 unit One fimm manufactures all items. It takes 2 weeks to make S. 1 week to make T. 2 weeks to make More info - X More info The product structure The time-phased product structure forde ompe Level 0 V w x On Hand Item Item e Inventory Ta S 1 On Hand Inventory 30 30 30 40 Y 5 T U V U W X Y 2 20 40 20 2 Vin Win X Vi har Tingin week Print Done Print Done Order release Enter your answer in the ed essind then ack Check Answer Homework: Study Plan 6 Save Score: 0 of 1 pt 6 of 14 (12 complete) HW Score: 75.29%, 10.54 of 14 p Problem 14.9 Question Help The demand for subassembly S is 90 units in week 7. Each unit of Srequires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of w, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make 1, 2 weeks to make u. 2 weeks to make V. 3 weeks to make W. 1 week to make X 2 weeks to make y, and 1 week to make Z Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory Suppose that in addition to 90 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are Weeded for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 90 units of due in week 8. Modify the net material requirements plan to reflect these changes Construct a new net material requirements plan (enter your responses as whole numbers). Item Week Lead Time 3 (weeks) s Gross reg 1 2 4 5 6 7 8 Enter your answer in the edit fields and then click Check Answer 7 parts remaining Clear All Ecore: 0 of 1 pt 6 of 14 (12 complete) HW Score: 75 29%, 1054 o Problem 14.9 0 More Info - X o The product structure The time-phased product structure. Level Q V Item Item 0 or T w X On-Hand Inventory 20 20 40 20 On-Hand Inventory 30 30 30 40 o os T(2) S T U V UU e w Y Z 1 Y Z U 2 V11) Will X (2) 7 (1) 2 (2) 2 Time in weeks Print Done OTT Print Done Score: 0 of 1 pt 6 of 14 (12 complete) HW Score: 75.29%, 10.54 of 14 Problem 14.9 Question Help Click the icon to view the on-hand inventory Suppose that in addition to 90 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 90 units of S due in week 8. Modify the net material requirements plan to reflect these changes Construct a new net material requirements plan (enter your responses as whole numbers). Item Week (weeks) Gross reg On hand Net reg 2 Order receipt Order release Lead Time 1 2 3 4 5 6 7 8 S LL Enter your answer in the edit fields and then click Check Answer 7 parts Clear All Check Answer remaining Problem 14.9 The demand for subassembly Sis 9 units in week 7. Each unit of requires 2 unts of and 1 unit of U. Each unt of requires 1 unt of 1 unit of W. and 2 units of X. Finally, each unit of requires 1 unt of Y and 2 unts of Z One firm mandatures all items. It takes 2 weeks to make S. 1 week to make T, 2 weeks to make u. 2 weeks to make V. 3 weeks to make W. 1 week to make X 2 weeks to make and 1 week to make 2 Click the icon to view the product structure and the time phased product structure TE Click the icon to view the on hand inventory Suppose that in addition to 90 units of S. there is a demand for 20 unts of which is a component of The 20 units of Ure reeded for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for sounds of due in week 8. Modify the mill requirements plan to reflect these changes Construct a new material requirements plan enter your responses a whole numbers Item Week Lead Time 1. 2 3 6 7 & 5 Gross reg On hand Netre 2 Onder recept Order release 4 5 Enter your answer in the edit fields and then click Check Answer 7 remaining core: 0 of 1 pt 6 of 14 (9 complete) HW Score: 44.5%, 6.23 of Question Help Problem 14.9 -X of The demand for subassembly S is 90 units in week 7. Each unit of requires 2 units of T and 1 unit One fimm manufactures all items. It takes 2 weeks to make S. 1 week to make T. 2 weeks to make More info - X More info The product structure The time-phased product structure forde ompe Level 0 V w x On Hand Item Item e Inventory Ta S 1 On Hand Inventory 30 30 30 40 Y 5 T U V U W X Y 2 20 40 20 2 Vin Win X Vi har Tingin week Print Done Print Done Order release Enter your answer in the ed essind then ack Check Answer Homework: Study Plan 6 Save Score: 0 of 1 pt 6 of 14 (12 complete) HW Score: 75.29%, 10.54 of 14 p Problem 14.9 Question Help The demand for subassembly S is 90 units in week 7. Each unit of Srequires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of w, and 2 units of X. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make 1, 2 weeks to make u. 2 weeks to make V. 3 weeks to make W. 1 week to make X 2 weeks to make y, and 1 week to make Z Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory Suppose that in addition to 90 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are Weeded for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 90 units of due in week 8. Modify the net material requirements plan to reflect these changes Construct a new net material requirements plan (enter your responses as whole numbers). Item Week Lead Time 3 (weeks) s Gross reg 1 2 4 5 6 7 8 Enter your answer in the edit fields and then click Check Answer 7 parts remaining Clear All Ecore: 0 of 1 pt 6 of 14 (12 complete) HW Score: 75 29%, 1054 o Problem 14.9 0 More Info - X o The product structure The time-phased product structure. Level Q V Item Item 0 or T w X On-Hand Inventory 20 20 40 20 On-Hand Inventory 30 30 30 40 o os T(2) S T U V UU e w Y Z 1 Y Z U 2 V11) Will X (2) 7 (1) 2 (2) 2 Time in weeks Print Done OTT Print Done Score: 0 of 1 pt 6 of 14 (12 complete) HW Score: 75.29%, 10.54 of 14 Problem 14.9 Question Help Click the icon to view the on-hand inventory Suppose that in addition to 90 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 90 units of S due in week 8. Modify the net material requirements plan to reflect these changes Construct a new net material requirements plan (enter your responses as whole numbers). Item Week (weeks) Gross reg On hand Net reg 2 Order receipt Order release Lead Time 1 2 3 4 5 6 7 8 S LL Enter your answer in the edit fields and then click Check Answer 7 parts Clear All Check Answer remaining