Problem 2 (10 Points, 2.5 points each, -1.25 per error) Do not solve these problemsformulate/define them only. You have a set of 14 potential projects
Problem 2 (10 Points, 2.5 points each, -1.25 per error)
Do not solve these problemsformulate/define them only.
You have a set of 14 potential projects from which you must select a subset of projects. We will use binary variables X1 ... X14, where if a project is selected, then its corresponding variable = 1, 0 otherwise. Formulate each of the four constraints below and ensure that you show your work and list your variables in the correct order. Note: You do not need to define the variables or the objective function for this problem.
Constraint 1) Project 14 could be selected if and only if all of Project 1, Project 2, Project 9, & Project 11 are selected.
Constraint 2) Project 11 must be selected if Project 3 is selected. Project 3 must be selected if Project 11 is selected.
Constraint 3) Project 9 must be selected if Project 8 is selected. The reverse is not true.
Constraint 4) Project 11 must be selected if all of Projects 1, 2, 3, 4, & 5 are selected.
Formulate the model using the headings listed below:
Constraints:
Additional Work for Constraints:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started