Question

1 Approved Answer

PROBLEM 2 : An activity on the critical path of a project was scheduled to be completed within 1 5 weeks with a budget of

PROBLEM 2:
An activity on the critical path of a project was scheduled to be completed within 15 weeks with a budget
of $9,000. During a performance review that took place 8 weeks after the activity was initiated, it was
found that 45% of the work had already been completed and that the actual cost was $5,200.
a.) Calculate the earned value of the activity.
b.) Calculate the cost and schedule indices for the activity.
c.) Calculate the expected duration and the expected total cost at completion using the cost index
and the schedule index.
d.) Present your conclusions. (What is going on with this activity?)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Marketing

Authors: Nigel Piercy and David Cravens

10th edition

78028906, 978-0078028908

More Books