Problem 2 Consider the following project network. The numbers represent activity times in weeks. Carry out a forward and backward path analysis and calculate ES

Problem 2
Consider the following project network. The numbers represent activity times in weeks.
Carry out a forward and backward path analysis and calculate ES, EF, LS, LF, and slack for each activity. Then please fill out the table below.
\table[[,Forward Pass,Backward Pass,Slack,],[Activity,Time,ES,EF,LS,LF,LF - EF,LS - ES,Slack],[A,2,,,,,,,],[B,1,,,,,,,],[C,1,,,,,,,],[E,3,,,,,,,],[H,5,,,,,,,],[I,5,,,,,,,],[J,4,,,,,,,]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management State Of The Field And Its Future

Authors: Irene M. Duhaime , Michael A. Hitt , Marjorie A. Lyles

1st Edition

0190090898, 978-0190090890

More Books

Students also viewed these General Management questions

Question

example of digital disruption to business

Answered: 1 week ago