Problem 3 (15 Points) Lily Construction Company was the low bidder on a construction project to build indoor batting cages for $1,800,000. The project was

Problem 3 (15 Points)

Lily Construction Company was the low bidder on a construction project to build indoor batting cages for $1,800,000.

The project was begun in 2017 and completed in 2018. Cost and other data are presented below:

Costs incurred during the year 2017-- $450,000 2018-- $1,100,000

Estimated costs to complete 2017---1,050,000 2018-- 0

Billings during the year 2017--400,000 2018--1,400,000

Cash collections during the year 2017--300,000 2018---1,500,000

Prepare the journal entries for 2017 and 2018 assuming Lily uses the percentage of completion method.

Prepare the revenue recognition journal entries for 2017 and 2018 assuming Lily uses the completed contract

method.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Forensic And Investigative Accounting

Authors: G. Stevenson Smith D. Larry Crumbley, Edmund D. Fenton

10th Edition

0808056301, 9780808056300

More Books

Students also viewed these Accounting questions