Problem 3 . (21 marks). At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert
Problem
3
.
(21 marks).
At a local university, the Student Commission on Programming and
Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To
successfully produce this rock concert, SCOPE has listed the requisite activities and related
informat
ion in the following table (duration estimates measured in days).
Activity
Immediate
Predecess
or(s)
Optimistic
Most
probable
Pessimisti
c
A: Negotiate contract with selected
musicians
---
8
10
15
B: Reserve site
---
7
8
9
C: Manage travel
logistics for music
group
A
5
6
10
D: Screen & hire security personnel
B
3
3
3
E: Arrange advertising & ticketing
B,C
1
5
9
F: Hire parking staff
D
4
7
10
G: Arrange concession sales
E
3
8
10
a.
(7 marks)
Draw the project network, indicating the earliest start, earliest finish, latest start,
and latest finish day of each activity.
b.
(2 marks)
What is the expected duration and variance of the critical path?
c.
(4 marks)
Based on the critical path, what is the likelihood that the project will be
completed within 30 days?
e.
(4 marks)
Based on the critical path, what is the likelihood that the project will be
completed in more than 25 days?
d.
(4 marks)
Based on the critical path, what deadline should be set so that the likelihood of
completing the project within that deadline is 75 %?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started