Problem 3 [ 3 0 pts ] Consider the following two - week ( 1 0 working days ) computer training class: Given the following.

Problem 3[30 pts]
Consider the following two-week (10 working days) computer training class:
Given the following.
Here activity B requires A and D cant starts before completing C. Both B and D are also necessary
to be completed for activity E? to be performed. The duration of these activities arse given in the
table above under column 'normal time'.
a) Construct the network and find the critical path while showing ES5,LSs,EF5,LEs, and
slacks for all activities.
b) Find the crash cost per day for each activity
c) Which activity (ias) should be crashed to meet a project deadline of 10 days with a
minimum coat? Assume partial crashing.
d) Find the new cost.
e) Is partial crashing an appropriate assumption in this kind of project?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Stage Management

Authors: Lawrence Stern, Jill Gold

12th Edition

0367647893, 978-0367647896

More Books

Students also viewed these General Management questions