Problem 3 The assembly of a dresser requires 9 tasks. The tasks, their precedence relationships, and the task times in minutes are given in the

Problem 3
The assembly of a dresser requires 9 tasks. The tasks, their precedence relationships, and the task times in minutes are given in the following table:
\table[[Tasks,\table[[Immediate],[Predecessor]],Task Time (in minutes)],[A,NONE,10],[B,A,2],[C,B,4],[D,B,6],[E,B,4],[F,C, D,8],[G,F,7],[H,E, F,6],[I,G, H,5],[Total,,52]]
a. Draw a precedence diagram that shows the precedence relationships among tasks for this assembly operation.
b. If 200 dressers are to be assembled in a 40-hour work week, what is the cycle time?
c. What is the minimum number of workstations required to balance this assembly line?
d. Assign tasks to workstations using the most-following-tasks rule as the primary rule and the ranked-positional-weight rule as the secondary (breaking tie) rule.
e. Compute the balance efficiency and percent delay (percent idle time).
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions

Question

Solve the following 1,4 3 2TT 5x- 1+ (15 x) dx 5X

Answered: 1 week ago