Problem 4 The following activities are part of a project to be scheduled by CPM / PERT: Activity Immediate Predecessor Optimistic Time Most Likely Time
Problem 4
The following activities are part of a project to be scheduled by CPM / PERT:
Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
A | --- | 2 | 4 | 8 |
B | A | 1 | 8 | 12 |
C | A | 4 | 5 | 12 |
D | A | 3 | 4 | 7 |
E | B | 1 | 2 | 5 |
F | C | 1 | 6 | 8 |
G | D | 1 | 8 | 9 |
H | E, F | 2 | 4 | 6 |
I | H | 2 | 9 | 12 |
J | G | 3 | 4 | 5 |
K | I, J | 5 | 6 | 9 |
Draw the network and determine the critical path based on expected completion time. Round the expected completion times for each activity to the nearest whole number. What activities are on the critical path?
What is the estimated completion time for the project? (Use the rounded answers from question 1).
What is the probability that the project will be completed within 35 days? (Use the exact values from Excel).
What is the probability that the project will be completed Within 28 Days? (Use the exact values from Excel).
We are 99% confident the project will be completed within how many days? (Use the exact values from Excel). (Hint: Use the excel function, NORM.INV, where Te is the expected or mean time.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started