Question
1 Approved Answer
Problem 4-7 (Static) The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 6 D B,
Problem 4-7 (Static) The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 6 D B, C D E , b. What is the critical path? O A-C-D-E-G O ABE-G OACD FG c. How many weeks will it take to complete the project? Number of weeksd. How much slack does activity B have? Slack of activity B weeks