Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Problem 5 . A copper leaching operation has a stockpile with an estimated ore capacity of 0 . 5 million tons and an average grade

Problem 5.
A copper leaching operation has a stockpile with an estimated ore capacity of 0.5 million tons and an average grade of 0.11%. The laboratory test conducted on the ore material indicated two possible leaching conditions.
Option 1 resulted in 67% recovery of the metal with daily reagent consumption 1200gm? ton of ore.
Option 2 resulted in 69% recovery of the metal with daily reagent consumption 1350gmton of ore.
Assuming leach cycle to be 180 days for both cases, reagent cost being $1.6kg and copper selling price to $3.5? lbs determine; i) Which option would be economical for operations to choose ii) At what reagent consumption for option 2 the mines will generate same cash flow.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Chemical Engineering Thermodynamics

Authors: J.M. Smith, Hendrick Van Ness, Michael Abbott, Mark Swihart

8th Edition

1259696529, 978-1259696527

More Books

Students also viewed these Chemical Engineering questions